BREAKDOWN OF UNIT PRICE
Item:1517. Precast Ventilator (1:2) - 25 mm
Basis:6sft
A2.Cement
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Cement: CEM-II/A,52.5-PCC
0.475
bag
405.00
192.38
Sub-Total(A2)
192.38
345.12
A4.Earth/ Sand
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand (F.M.1.2)
2.625
cft
19.00
49.88
Sub-Total(A4)
49.88
89.48
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour
0.680
No.
550.00
374.00
Mason
0.885
No.
700.00
619.50
Head Mason
0.045
No.
800.00
36.00
Sub-Total(L1)
1029.50
1846.92
M2.Local Carriage,Sundr
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Local Carriage-(Labour)
0.120
No.
550.00
66.00
Sub-Total(M2)
66.00
118.40
Total(1)
2399.92
Add over head on Total(1)
3.5 %
84.00
Add Profit on Total(1)
10.0 %
239.99
Total(2)
323.99
Add VAT on Unit Price
5.5 %
18.86
Unit Price
342.85
Say
343
per sqm