BREAKDOWN OF UNIT PRICE
Item:151502. Water/damp proof plaster -19mm
Basis:100sft
A2.Cement
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Cement: CEM-II/A,52.5-PCC
0.280
bag
405.00
113.40
Water/damp proof cement
2.270
bag
1800.00
4086.00
Sub-Total(A2)
4199.40
452.02
A4.Earth/ Sand
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand (F.M.1.2)
7.880
cft
19.00
149.72
Sub-Total(A4)
149.72
16.12
E1.Equipment/ Scaffoldi
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mixer m/c hire charge
0.100
day
1200.00
120.00
Sub-Total(E1)
120.00
12.92
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour
1.000
No.
550.00
550.00
Mason
1.000
No.
700.00
700.00
Head Mason
0.250
No.
800.00
200.00
Sub-Total(L1)
1450.00
156.08
M2.Local Carriage,Sundr
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Local Carriage-(Labour)
0.667
No.
550.00
366.85
Sub-Total(M2)
366.85
39.49
Total(1)
676.62
Add over head on Total(1)
3.5 %
23.68
Add Profit on Total(1)
10.0 %
67.66
Total(2)
91.34
Add VAT on Unit Price
5.5 %
5.32
Unit Price
96.66
Say
97
per sqm