BREAKDOWN OF UNIT PRICE
Item:1509. Raised/ Tack Pointing (1:2) -GF
Basis:100sft
A2.Cement
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Cement: CEM-II/A,52.5-PCC
1.000
bag
405.00
405.00
Sub-Total(A2)
405.00
43.59
A3.Stone/ Mosaic/ Admix
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Pumice stone
0.250
each
175.00
43.75
Sub-Total(A3)
43.75
4.71
A4.Earth/ Sand
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand (F.M.1.2)
3.000
cft
19.00
57.00
Sub-Total(A4)
57.00
6.14
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour
2.000
No.
550.00
1100.00
Mason
2.000
No.
700.00
1400.00
Skilled Labour
2.000
No.
600.00
1200.00
Head Mason
0.200
No.
800.00
160.00
Sub-Total(L1)
3860.00
415.49
M2.Local Carriage,Sundr
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Local Carriage-(Labour)
0.444
No.
550.00
244.20
Sub-Total(M2)
244.20
26.29
Total(1)
496.22
Add over head on Total(1)
3.5 %
17.37
Add Profit on Total(1)
10.0 %
49.62
Total(2)
66.99
Add VAT on Unit Price
5.5 %
3.90
Unit Price
70.89
Say
71
per sqm