BREAKDOWN OF UNIT PRICE
Item:1424. Tempered Glass-12mm thick-6-8.2m
Basis:225sft
C1.Aluminium Channel
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Glass Clear Tempered-12mm
373.750
sft
400.00
149500.00
Sub-Total(C1)
149500.00
7152.08
C2.Alum/ PVC Accessoris
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
SS Screws-50mm
80.000
pcs
2.50
200.00
Steel Rowel Bolt
24.000
pcs
42.00
1008.00
Masking Tape
8.000
pcs
25.00
200.00
Sealant Gum
8.000
pcs
405.00
3240.00
Fin connector
8.000
nos
4430.00
35440.00
Fin hanger
8.000
nos
5245.00
41960.00
Nut-bolt
24.000
pcs
32.00
768.00
SS U Channel
18.000
rft
205.00
3690.00
SS spider set
12.000
nos
9500.00
114000.00
Sub-Total(C2)
200506.00
9592.21
E1.Equipment/ Scaffoldi
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Scaffolding
85.938
sft
10.00
859.38
Curtain Wall-Machineries
0.500
LS
1718.75
859.38
Sub-Total(E1)
1718.76
82.23
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Alum.Skilled Technicians
15.000
No.
1200.00
18000.00
Alum.Semi-skill Techn
15.000
No.
800.00
12000.00
Sub-Total(L1)
30000.00
1435.20
M2.Local Carriage,Sundr
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Local Carriage-(Labour)
2.500
No.
550.00
1375.00
Sub-Total(M2)
1375.00
65.78
Total(1)
18327.49
Add over head on Total(1)
3.5 %
641.46
Add Profit on Total(1)
10.0 %
1832.75
Total(2)
2474.21
Add VAT on Unit Price
5.5 %
144.00
Unit Price
2618.21
Say
2618
per sqm