BREAKDOWN OF UNIT PRICE
Item:1311. Ver Grill -20mm Rod 100mm c/c
Basis:32sft
F2.Steel-MS/ SS
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
MS Rod 300 grade/ 40 grad
74.723
kg
65.00
4857.00
MS Angle/ Z section
77.153
kg
70.00
5400.71
Sub-Total(F2)
10257.71
3505.20
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mason
0.500
No.
700.00
350.00
Helper
0.500
No.
550.00
275.00
Sub-Total(L1)
625.00
213.57
L2.Work Rate-1
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Grill Rod/ FI Bar Fabrica
31.500
sft
51.00
1606.50
Sub-Total(L2)
1606.50
548.96
M1.Miscelleneous
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
CC, Curing-Grill
3.388
LS
150.00
508.20
Sub-Total(M1)
508.20
173.66
M2.Local Carriage,Sundr
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Local Carriage-(Labour)
0.150
No.
550.00
82.50
Sub-Total(M2)
82.50
28.19
Total(1)
4469.59
Add over head on Total(1)
3.5 %
156.44
Add Profit on Total(1)
10.0 %
446.96
Total(2)
603.39
Add VAT on Unit Price
5.5 %
35.12
Unit Price
638.51
Say
639
per sqm