BREAKDOWN OF UNIT PRICE
Item:1310. MS Window Grill-25mm Rod@75mm c/c
Basis:23sft
F2.Steel-MS/ SS
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
MS Rod 300 grade/ 40 grad
105.676
kg
65.00
6868.94
MS Angle/ Z section
82.251
kg
70.00
5757.57
Sub-Total(F2)
12626.51
6040.52
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mason
0.750
No.
700.00
525.00
Helper
0.750
No.
550.00
412.50
Sub-Total(L1)
937.50
448.50
L2.Work Rate-1
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Grill Rod/ FI Bar Fabrica
22.500
sft
51.00
1147.50
Sub-Total(L2)
1147.50
548.96
M1.Miscelleneous
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
CC, Curing-Grill
3.388
LS
150.00
508.20
Sub-Total(M1)
508.20
243.12
M2.Local Carriage,Sundr
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Local Carriage-(Labour)
0.150
No.
550.00
82.50
Sub-Total(M2)
82.50
39.47
Total(1)
7320.58
Add over head on Total(1)
3.5 %
256.22
Add Profit on Total(1)
10.0 %
732.06
Total(2)
988.28
Add VAT on Unit Price
5.5 %
57.52
Unit Price
1045.80
Say
1046
per sqm