Return Main Menu
BREAKDOWN OF UNIT PRICE
Item:1309. Ver Grill-MS Hollow box
Basis:68sft
F2.Steel-MS/ SS
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
MS Flat (FI) Bar
2.318
kg
70.00
162.26
MS Hollow Box
133.443
kg
139.93
18672.68
Sub-Total(F2)
18834.94
2970.54
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mason
1.000
No.
700.00
700.00
Helper
1.000
No.
550.00
550.00
Sub-Total(L1)
1250.00
197.14
L2.Work Rate-1
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Grill Rod/ FI Bar Fabrica
68.250
sft
51.00
3480.75
Sub-Total(L2)
3480.75
548.96
M1.Miscelleneous
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
CC, Curing-Grill
1.000
LS
150.00
150.00
Sub-Total(M1)
150.00
23.66
M2.Local Carriage,Sundr
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Local Carriage-(Labour)
0.364
No.
550.00
200.20
Sub-Total(M2)
200.20
31.57
Total(1)
3771.88
Add over head on Total(1)
3.5 %
132.02
Add Profit on Total(1)
10.0 %
377.19
Total(2)
509.20
Add VAT on Unit Price
5.5 %
29.64
Unit Price
538.84
Say
539
per sqm