BREAKDOWN OF UNIT PRICE
Item:1308. Ver Grill-Box-Bar-Emergency Exit
Basis:59sft
F2.Steel-MS/ SS
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
MS Flat (FI) Bar
2.318
kg
70.00
162.26
MS Solid Squar Bar
80.420
kg
69.85
5617.34
MS Hollow Box
69.640
kg
139.93
9744.73
Sub-Total(F2)
15524.32
2837.08
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mason
1.000
No.
700.00
700.00
Helper
1.000
No.
550.00
550.00
Sub-Total(L1)
1250.00
228.44
L2.Work Rate-1
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Grill Rod/ FI Bar Fabrica
58.900
sft
51.00
3003.90
Sub-Total(L2)
3003.90
548.96
M1.Miscelleneous
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
CC, Curing-Grill
1.000
LS
150.00
150.00
Emergency Exit-750x750
1.000
no.
1000.00
1000.00
Sub-Total(M1)
1150.00
210.16
M2.Local Carriage,Sundr
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Local Carriage-(Labour)
0.364
No.
550.00
200.20
Sub-Total(M2)
200.20
36.59
Total(1)
3861.23
Add over head on Total(1)
3.5 %
135.14
Add Profit on Total(1)
10.0 %
386.12
Total(2)
521.27
Add VAT on Unit Price
5.5 %
30.34
Unit Price
551.60
Say
552
per sqm