BREAKDOWN OF UNIT PRICE
Item:130505. Window Grill -12x12 Hollow Box
Basis:29sft
F2.Steel-MS/ SS
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
MS Hollow Box-12x12
47.727
kg
105.60
5039.97
Sub-Total(F2)
5039.97
1854.71
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mason
0.500
No.
700.00
350.00
Helper
0.500
No.
550.00
275.00
Sub-Total(L1)
625.00
230.00
L2.Work Rate-1
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
MS Grill-Solid/Hollow fab
29.250
sft
51.00
1491.75
Sub-Total(L2)
1491.75
548.96
M1.Miscelleneous
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
CC, Curing-Grill
1.000
LS
150.00
150.00
Sub-Total(M1)
150.00
55.20
M2.Local Carriage,Sundr
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Local Carriage-(Labour)
0.250
No.
550.00
137.50
Sub-Total(M2)
137.50
50.60
Total(1)
2739.47
Add over head on Total(1)
3.5 %
95.88
Add Profit on Total(1)
10.0 %
273.95
Total(2)
369.83
Add VAT on Unit Price
5.5 %
21.52
Unit Price
391.35
Say
391
per sqm