BREAKDOWN OF UNIT PRICE
Item:130501. Wind Grill -10x10 Solid Bar-38x6
Basis:29sft
F2.Steel-MS/ SS
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
MS Flat (FI) Bar
15.759
kg
70.00
1103.13
MS Solid Squar Bar
31.195
kg
69.85
2178.97
Sub-Total(F2)
3282.10
1207.81
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mason
0.750
No.
700.00
525.00
Helper
0.750
No.
550.00
412.50
Sub-Total(L1)
937.50
345.00
L2.Work Rate-1
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
MS Grill-Solid/Hollow fab
29.250
sft
51.00
1491.75
Sub-Total(L2)
1491.75
548.96
M1.Miscelleneous
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
CC, Curing-Grill
1.000
LS
150.00
150.00
Sub-Total(M1)
150.00
55.20
M2.Local Carriage,Sundr
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Local Carriage-(Labour)
0.150
No.
550.00
82.50
Sub-Total(M2)
82.50
30.36
Total(1)
2187.34
Add over head on Total(1)
3.5 %
76.56
Add Profit on Total(1)
10.0 %
218.73
Total(2)
295.29
Add VAT on Unit Price
5.5 %
17.19
Unit Price
312.48
Say
312
per sqm