BREAKDOWN OF UNIT PRICE
Item:130301. Window Grill-FI Bar-Out-Iner-20x5
Basis:24s
F2.Steel-MS/ SS
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
MS Flat (FI) Bar
24.159
kg
70.00
1691.13
Sub-Total(F2)
1691.13
70.51
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mason
0.500
No.
700.00
350.00
Helper
0.500
No.
550.00
275.00
Sub-Total(L1)
625.00
26.06
L2.Work Rate-1
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Grill Rod/ FI Bar Fabrica
23.985
sft
51.00
1223.24
Sub-Total(L2)
1223.24
51.00
M1.Miscelleneous
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
CC, Curing-Grill
1.000
LS
150.00
150.00
Sub-Total(M1)
150.00
6.25
M2.Local Carriage,Sundr
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Local Carriage-(Labour)
0.150
No.
550.00
82.50
Sub-Total(M2)
82.50
3.44
Total(1)
157.26
Add over head on Total(1)
3.5 %
5.50
Add Profit on Total(1)
10.0 %
15.73
Total(2)
21.23
Add VAT on Unit Price
5.5 %
1.24
Unit Price
22.47
Say
22
per sqm