Return Main Menu
BREAKDOWN OF UNIT PRICE
Item:121104. Glaze Vent Louvr Shutter-Bur Teak
Basis:13sft
C3.Plastic Door/Win/Par
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Glass-5mm thick clear
10.250
sft
71.00
727.75
Sub-Total(C3)
727.75
586.78
E1.Equipment/ Scaffoldi
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Seasoning Timber
2.627
cft
165.00
433.46
Sub-Total(E1)
433.46
349.49
F1.Timber/ Board
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Burma teak wood
2.627
cft
7100.00
18651.70
Sub-Total(F1)
18651.70
15038.72
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Helper
1.500
No.
550.00
825.00
Carpenter
1.000
No.
700.00
700.00
Sub-Total(L1)
1525.00
1229.60
L2.Work Rate-1
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Labour-Seasoning Timber
5.254
cft
55.00
288.97
Sub-Total(L2)
288.97
232.99
M1.Miscelleneous
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Nail, screw, bit, putty
1.000
LS
25.00
25.00
Sub-Total(M1)
25.00
20.16
Total(1)
17457.74
Add over head on Total(1)
3.5 %
611.02
Add Profit on Total(1)
10.0 %
1745.77
Total(2)
2356.79
Add VAT on Unit Price
5.5 %
137.17
Unit Price
2493.96
Say
2494
per sqm