Return Main Menu
BREAKDOWN OF UNIT PRICE
Item:1209011. Venear Solid Flush Door-BurmTk-SS
Basis:20sft
F1.Timber/ Board
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
VeneeredFlush Door-B.Teak
20.250
sft
340.00
6885.00
Sub-Total(F1)
6885.00
3659.76
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Helper
0.500
No.
550.00
275.00
Carpenter
0.250
No.
700.00
175.00
Sub-Total(L1)
450.00
239.20
M1.Miscelleneous
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Nickel plate handle
2.000
No.
80.00
160.00
Hinged cleat,buffer block
1.000
set
62.00
62.00
SS Socket Bolt-200 mm
1.000
No.
220.00
220.00
SS Hing-100mm
4.000
No.
100.00
400.00
SS Screw
5.000
dozn
30.00
150.00
SS Tower Bolt-250 mm
1.000
No.
150.00
150.00
Sub-Total(M1)
1142.00
607.04
Total(1)
4506.00
Add over head on Total(1)
3.5 %
157.71
Add Profit on Total(1)
10.0 %
450.60
Total(2)
608.31
Add VAT on Unit Price
5.5 %
35.40
Unit Price
643.71
Say
644
per sqm