BREAKDOWN OF UNIT PRICE
Item:1101052. Door Frame-CTG Teak-2.5x11 in
Basis:3cft
F1.Timber/ Board
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Chittagong teak wood
3.059
cft
4400.00
13459.60
Sub-Total(F1)
13459.60
175851.19
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Helper
0.250
No.
550.00
137.50
Carpenter
1.000
No.
700.00
700.00
Sub-Total(L1)
837.50
10942.03
L3.Work Rate i/c Materi
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Coal-tar over timber surf
13.000
sft
8.20
106.60
Dr Frame-Mehgoni/Garj fix
1.000
No.
300.00
300.00
Sub-Total(L3)
406.60
5312.27
Total(1)
192105.50
Add over head on Total(1)
3.5 %
6723.69
Add Profit on Total(1)
10.0 %
19210.55
Total(2)
25934.24
Add VAT on Unit Price
5.5 %
1509.40
Unit Price
27443.64
Say
27444
per cum