Return Main Menu
BREAKDOWN OF UNIT PRICE
Item:1101051. Door Frame-CTG Teak-2.5x6 in
Basis:2cft
F1.Timber/ Board
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Chittagong teak wood
1.750
cft
4400.00
7700.00
Sub-Total(F1)
7700.00
181283.67
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Helper
0.250
No.
550.00
137.50
Carpenter
1.000
No.
700.00
700.00
Sub-Total(L1)
837.50
19717.54
L3.Work Rate i/c Materi
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Coal-tar over timber surf
6.500
sft
8.20
53.30
Dr Frame-Mehgoni/Garj fix
1.000
No.
300.00
300.00
Sub-Total(L3)
353.30
8317.86
Total(1)
209319.07
Add over head on Total(1)
3.5 %
7326.17
Add Profit on Total(1)
10.0 %
20931.91
Total(2)
28258.07
Add VAT on Unit Price
5.5 %
1644.65
Unit Price
29902.72
Say
29903
per cum