BREAKDOWN OF UNIT PRICE
Item:1101032. Door Frame-Silkoroi/Loha-2.5x11in
Basis:3cft
F1.Timber/ Board
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Silkarai/ Azob/ Loha Wood
3.059
cft
2500.00
7647.50
Sub-Total(F1)
7647.50
99915.45
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Helper
0.250
No.
550.00
137.50
Carpenter
1.000
No.
700.00
700.00
Sub-Total(L1)
837.50
10942.03
L3.Work Rate i/c Materi
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Coal-tar over timber surf
13.000
sft
8.20
106.60
Dr Frame-Mehgoni/Garj fix
1.000
No.
300.00
300.00
Sub-Total(L3)
406.60
5312.27
Total(1)
116169.76
Add over head on Total(1)
3.5 %
4065.94
Add Profit on Total(1)
10.0 %
11616.98
Total(2)
15682.92
Add VAT on Unit Price
5.5 %
912.76
Unit Price
16595.68
Say
16596
per cum