BREAKDOWN OF UNIT PRICE
Item:1101031. Door Frame-Silkoroi/ Loha-2.5x6in
Basis:2cft
F1.Timber/ Board
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Silkarai/ Azob/ Loha Wood
1.750
cft
2500.00
4375.00
Sub-Total(F1)
4375.00
103002.08
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Helper
0.250
No.
550.00
137.50
Carpenter
1.000
No.
700.00
700.00
Sub-Total(L1)
837.50
19717.54
L3.Work Rate i/c Materi
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Coal-tar over timber surf
6.500
sft
8.20
53.30
Dr Frame-Mehgoni/Garj fix
1.000
No.
300.00
300.00
Sub-Total(L3)
353.30
8317.86
Total(1)
131037.48
Add over head on Total(1)
3.5 %
4586.31
Add Profit on Total(1)
10.0 %
13103.75
Total(2)
17690.06
Add VAT on Unit Price
5.5 %
1029.58
Unit Price
18719.64
Say
18720
per cum