Return Main Menu
BREAKDOWN OF UNIT PRICE
Item:1101022. Door Frame-Garjan/Jam/Sal-2.5x11"
Basis:3cft
F1.Timber/ Board
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Garjan/Jam/Local Sal wood
3.059
cft
2200.00
6729.80
Sub-Total(F1)
6729.80
87925.60
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Helper
0.250
No.
550.00
137.50
Carpenter
1.000
No.
700.00
700.00
Sub-Total(L1)
837.50
10942.03
L3.Work Rate i/c Materi
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Coal-tar over timber surf
13.000
sft
8.20
106.60
Dr Frame-Mehgoni/Garj fix
1.000
No.
300.00
300.00
Sub-Total(L3)
406.60
5312.27
Total(1)
104179.90
Add over head on Total(1)
3.5 %
3646.30
Add Profit on Total(1)
10.0 %
10417.99
Total(2)
14064.29
Add VAT on Unit Price
5.5 %
818.56
Unit Price
14882.84
Say
14883
per cum