BREAKDOWN OF UNIT PRICE
Item:1030. Safety Net with GI Wire
Basis:739sft
F2.Steel-MS/ SS
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
MS Rod 400 grade/ 60 grad
128.455
kg
72.00
9248.76
MS Angle/ Z section
44.610
kg
70.00
3122.70
MS Channel
261.400
kg
70.00
18298.00
Safet Net-ChainLink-24BWG
387.760
sft
25.00
9694.00
Sub-Total(F2)
40363.46
588.25
L2.Work Rate-1
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Safety Net/Shed Fabricat
868.930
sft
25.00
21723.25
Safety net/Shed fixing
738.590
sft
30.00
22157.70
Sub-Total(L2)
43880.95
639.51
M2.Local Carriage,Sundr
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Local Carriage-(Labour)
0.909
No.
550.00
499.95
Sub-Total(M2)
499.95
7.29
Total(1)
1235.04
Add over head on Total(1)
3.5 %
43.23
Add Profit on Total(1)
10.0 %
123.50
Total(2)
166.73
Add VAT on Unit Price
5.5 %
9.70
Unit Price
176.43
Say
176
per sqm