BREAKDOWN OF UNIT PRICE
Item:1021. CI Sheet Roofing-0.457mm-Galvani
Basis:150sft
F1.Timber/ Board
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Bamboo-20 ft- use 6 times
3.000
No.
45.00
135.00
Sub-Total(F1)
135.00
9.69
F2.Steel-MS/ SS
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
CI Sheet-.457mm-Galvanize
150.000
sft
65.03
9754.50
Screw, limet, washer etc
150.000
sft
1.03
154.50
Sub-Total(F2)
9909.00
711.07
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour
0.750
No.
550.00
412.50
Helper
0.375
No.
550.00
206.25
Carpenter
0.750
No.
700.00
525.00
Sub-Total(L1)
1143.75
82.08
Total(1)
802.83
Add over head on Total(1)
3.5 %
28.10
Add Profit on Total(1)
10.0 %
80.28
Total(2)
108.38
Add VAT on Unit Price
5.5 %
6.31
Unit Price
114.69
Say
115
per sqm