BREAKDOWN OF UNIT PRICE
Item:1018. Chequred Plate-8mm-345 Mpa
Basis:1000kg.
F2.Steel-MS/ SS
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Checqured Plate-8mm-345Mp
1030.000
kg
138.00
142140.00
Sub-Total(F2)
142140.00
142140.00
F4.Paint
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Red oxide primer
12.000
litr
180.00
2160.00
Sub-Total(F4)
2160.00
2160.00
F5.Polish
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Wood Varnish Thinner
4.000
litr
131.00
524.00
Sub-Total(F5)
524.00
524.00
L2.Work Rate-1
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Red oxide primer apply
1000.000
kg
0.60
600.00
Sub-Total(L2)
600.00
600.00
L3.Work Rate i/c Materi
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Chequred Plate Fabricatio
1000.000
kg
12.00
12000.00
Sub-Total(L3)
12000.00
12000.00
M2.Local Carriage,Sundr
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Local Carriage-Load-Unloa
1000.000
kg
1.70
1700.00
Sub-Total(M2)
1700.00
1700.00
Total(1)
159124.00
Add over head on Total(1)
3.5 %
5569.34
Add Profit on Total(1)
10.0 %
15912.40
Total(2)
21481.74
Add VAT on Unit Price
5.5 %
1250.26
Unit Price
22732.00
Say
22732
per ton