BREAKDOWN OF UNIT PRICE |
Item:1008. Hot Roll Steel Shore Pile-250 Mpa |
Basis:1000kg. | |
F2.Steel-MS/ SS |
|
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Hot Rol Shore Pile-250Mpa | 1020.000 | kg |
80.00 | |
|
Less Salvage Hot Rol Shor | 1020.000 | kg |
-48.00 | |
|
|
Sub-Total(F2) |
32640.00
|
32640.00
|
F4.Paint |
|
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Red oxide primer | 12.000 | litr |
180.00 | |
|
|
Sub-Total(F4) |
2160.00
|
2160.00
|
F5.Polish |
|
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Wood Varnish Thinner | 4.000 | litr |
131.00 | |
|
|
Sub-Total(F5) |
524.00
|
524.00
|
L2.Work Rate-1 |
|
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Red oxide primer apply | 1000.000 | kg |
0.60 | |
|
|
Sub-Total(L2) |
600.00
|
600.00
|
L3.Work Rate i/c Materi |
|
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Hot Rol Shore Pile Fabric | 1000.000 | kg |
5.00 | |
|
|
Sub-Total(L3) |
5000.00
|
5000.00
|
M2.Local Carriage,Sundr |
|
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Local Carriage-Load-Unloa | 1000.000 | kg |
1.70 | |
|
|
Sub-Total(M2) |
1700.00
|
1700.00
|
|
|
|
Total(1) |
|
42624.00 |
|
Add over head on Total(1)
|
3.5 % |
1491.84 |
|
Add Profit on Total(1) |
10.0 % |
4262.40
|
|
|
|
Total(2) |
|
5754.24 |
|
Add VAT on Unit Price |
5.5 % |
334.90 |
|
|
|
Unit Price |
|
6089.14
|
|
|
|
Say |
6089 |
per ton |