BREAKDOWN OF UNIT PRICE
Item:0918. Precast pile auto drive-250x250mm
Basis:220rft
E1.Equipment/ Scaffoldi
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Auto Rig, crane,Gene,hamm
1.000
day
25200.00
25200.00
Sub-Total(E1)
25200.00
375.82
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Skilled Labour
6.000
No.
600.00
3600.00
Foreman/ Supervisor
2.000
No.
850.00
1700.00
Diesel operate rig driver
1.000
No.
700.00
700.00
Helper to rig driver
8.000
No.
550.00
4400.00
Sub-Total(L1)
10400.00
155.10
M1.Miscelleneous
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Fuel for auto rig
1.000
day
2500.00
2500.00
Sub-Total(M1)
2500.00
37.28
M2.Local Carriage,Sundr
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Local Carriage-(Labour)
0.909
No.
550.00
499.95
Sub-Total(M2)
499.95
7.46
Total(1)
575.67
Add over head on Total(1)
3.5 %
20.15
Add Profit on Total(1)
10.0 %
57.57
Total(2)
77.71
Add VAT on Unit Price
5.5 %
4.52
Unit Price
82.24
Say
82
per metr