BREAKDOWN OF UNIT PRICE
Item:0913. Pre-cast Pile Shoe
Basis:1no.
F2.Steel-MS/ SS
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
MS Rod 300 grade/ 40 grad
5.909
kg
65.00
384.09
MS Plate-250 MPa
7.605
kg
77.00
585.59
Sub-Total(F2)
969.67
969.67
L2.Work Rate-1
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Pile Shoe making
1.000
No.
1100.00
1100.00
Sub-Total(L2)
1100.00
1100.00
L3.Work Rate i/c Materi
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Joint Welding
56.000
inch
5.00
280.00
Sub-Total(L3)
280.00
280.00
M2.Local Carriage,Sundr
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Local Carriage-(Labour)
0.500
No.
550.00
275.00
Sub-Total(M2)
275.00
275.00
Total(1)
2624.67
Add over head on Total(1)
3.5 %
91.86
Add Profit on Total(1)
10.0 %
262.47
Total(2)
354.33
Add VAT on Unit Price
5.5 %
20.62
Unit Price
374.95
Say
375
per ea