BREAKDOWN OF UNIT PRICE |
Item:0908061. Static Load Test-200 ton-1st test |
Basis:1no. | |
A4.Earth/ Sand |
|
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Sand (FM=0.8) | 1823.000 | cft |
16.70 | |
|
|
Sub-Total(A4) |
30444.10
|
30444.10
|
E1.Equipment/ Scaffoldi |
|
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Hire Load TestEquip<=200t | 1.000 | test |
7000.00 | |
|
|
Sub-Total(E1) |
7000.00
|
7000.00
|
L1.Labour-Civil |
|
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Ordinary Labour | 14.000 | No. |
550.00 | |
|
Skilled Labour | 7.000 | No. |
600.00 | |
|
Foreman/ Supervisor | 2.000 | No. |
850.00 | |
|
|
Sub-Total(L1) |
13600.00
|
13600.00
|
L2.Work Rate-1 |
|
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Load-test platform making | 200.000 | ton |
275.00 | |
|
Fill,stich,load,unload | 7291.000 | bag |
12.00 | |
|
|
Sub-Total(L2) |
142492.00
|
142492.00
|
M1.Miscelleneous |
|
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Empty Gunny bag-use 2 tim | 3646.000 | bag |
5.00 | |
|
Load test result preparat | 1.000 | test |
6500.00 | |
|
|
Sub-Total(M1) |
24730.00
|
24730.00
|
M2.Local Carriage,Sundr |
|
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Local Carriage-(Labour) | 2.000 | No. |
550.00 | |
|
|
Sub-Total(M2) |
1100.00
|
1100.00
|
|
|
|
Total(1) |
|
219366.10 |
|
Add over head on Total(1)
|
3.5 % |
7677.81 |
|
Add Profit on Total(1) |
10.0 % |
21936.61
|
|
|
|
Total(2) |
|
29614.42 |
|
Add VAT on Unit Price |
5.5 % |
1723.59 |
|
|
|
Unit Price |
|
31338.01
|
|
|
|
Say |
31338 |
per test |