BREAKDOWN OF UNIT PRICE |
Item:0908041. Static Load Test-100 ton-1st test |
Basis:1no. | |
A4.Earth/ Sand |
|
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Sand (FM=0.8) | 911.500 | cft |
16.70 | |
|
|
Sub-Total(A4) |
15222.05
|
15222.05
|
E1.Equipment/ Scaffoldi |
|
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Hire Load TestEquip<=200t | 1.000 | test |
7000.00 | |
|
|
Sub-Total(E1) |
7000.00
|
7000.00
|
L1.Labour-Civil |
|
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Ordinary Labour | 12.000 | No. |
550.00 | |
|
Skilled Labour | 6.000 | No. |
600.00 | |
|
Foreman/ Supervisor | 2.000 | No. |
850.00 | |
|
|
Sub-Total(L1) |
11900.00
|
11900.00
|
L2.Work Rate-1 |
|
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Load-test platform making | 100.000 | ton |
275.00 | |
|
Fill,stich,load,unload | 3646.000 | bag |
12.00 | |
|
|
Sub-Total(L2) |
71252.00
|
71252.00
|
M1.Miscelleneous |
|
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Empty Gunny bag-use 2 tim | 1823.000 | bag |
5.00 | |
|
Load test result preparat | 1.000 | test |
6500.00 | |
|
|
Sub-Total(M1) |
15615.00
|
15615.00
|
M2.Local Carriage,Sundr |
|
Item |
Quantity |
Unit |
Rate(Tk.) |
Cost(Tk.) |
Rate(Tk.) |
Local Carriage-(Labour) | 2.000 | No. |
550.00 | |
|
|
Sub-Total(M2) |
1100.00
|
1100.00
|
|
|
|
Total(1) |
|
122089.05 |
|
Add over head on Total(1)
|
3.5 % |
4273.12 |
|
Add Profit on Total(1) |
10.0 % |
12208.91
|
|
|
|
Total(2) |
|
16482.02 |
|
Add VAT on Unit Price |
5.5 % |
959.27 |
|
|
|
Unit Price |
|
17441.29
|
|
|
|
Say |
17441 |
per test |