Return Main Menu
BREAKDOWN OF UNIT PRICE
Item:0907. Pile head breaking
Basis:35cft
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour
3.000
No.
550.00
1650.00
Skilled Labour
1.000
No.
600.00
600.00
Sub-Total(L1)
2250.00
2250.00
L3.Work Rate i/c Materi
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Prepare Pile head
1.000
LS
250.00
250.00
Sub-Total(L3)
250.00
250.00
M2.Local Carriage,Sundr
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Local Carriage-(Labour)
0.781
No.
550.00
429.55
Sub-Total(M2)
429.55
429.55
Total(1)
2929.55
Add over head on Total(1)
3.5 %
102.53
Add Profit on Total(1)
10.0 %
292.96
Total(2)
395.49
Add VAT on Unit Price
5.5 %
23.02
Unit Price
418.51
Say
419
per cum