BREAKDOWN OF UNIT PRICE
Item:090104. In-situ Pile Boring - 550 mm dia
Basis:52rft
E1.Equipment/ Scaffoldi
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
In-situ piling rig-hire
1.000
day
8500.00
8500.00
Sub-Total(E1)
8500.00
531.25
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour
6.000
No.
550.00
3300.00
Skilled Labour
3.000
No.
600.00
1800.00
Foreman/ Supervisor
1.000
No.
850.00
850.00
Sub-Total(L1)
5950.00
371.88
M1.Miscelleneous
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Bentoniote
114.040
kg
36.00
4105.44
Power, water,clean,sundry
1.000
LS
429.69
429.69
Sub-Total(M1)
4535.13
283.45
Total(1)
1186.57
Add over head on Total(1)
3.5 %
41.53
Add Profit on Total(1)
10.0 %
118.66
Total(2)
160.19
Add VAT on Unit Price
5.5 %
9.32
Unit Price
169.51
Say
170
per metr