BREAKDOWN OF UNIT PRICE
Item:090103. In-situ Pile Boring - 500 mm dia
Basis:62rft
E1.Equipment/ Scaffoldi
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
In-situ piling rig-hire
1.000
day
8500.00
8500.00
Sub-Total(E1)
8500.00
447.37
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour
6.000
No.
550.00
3300.00
Skilled Labour
3.000
No.
600.00
1800.00
Foreman/ Supervisor
1.000
No.
850.00
850.00
Sub-Total(L1)
5950.00
313.16
M1.Miscelleneous
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Bentoniote
111.919
kg
36.00
4029.08
Power, water,clean,sundry
1.000
LS
429.69
429.69
Sub-Total(M1)
4458.77
234.67
Total(1)
995.20
Add over head on Total(1)
3.5 %
34.83
Add Profit on Total(1)
10.0 %
99.52
Total(2)
134.35
Add VAT on Unit Price
5.5 %
7.82
Unit Price
142.17
Say
142
per metr