BREAKDOWN OF UNIT PRICE
Item:090102. In-situ Pile Boring - 450 mm dia
Basis:72rft
E1.Equipment/ Scaffoldi
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
In-situ piling rig-hire
1.000
day
8500.00
8500.00
Sub-Total(E1)
8500.00
386.36
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour
6.000
No.
550.00
3300.00
Skilled Labour
3.000
No.
600.00
1800.00
Foreman/ Supervisor
1.000
No.
850.00
850.00
Sub-Total(L1)
5950.00
270.45
M1.Miscelleneous
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Bentoniote
104.969
kg
36.00
3778.88
Power, water,clean,sundry
1.000
LS
429.69
429.69
Sub-Total(M1)
4208.57
191.30
Total(1)
848.12
Add over head on Total(1)
3.5 %
29.68
Add Profit on Total(1)
10.0 %
84.81
Total(2)
114.50
Add VAT on Unit Price
5.5 %
6.66
Unit Price
121.16
Say
121
per metr