BREAKDOWN OF UNIT PRICE
Item:072002. Water proof membrane floor-tempo
Basis:108sft
A3.Stone/ Mosaic/ Admix
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Water proof membran-Floor
118.404
sft
53.88
6379.61
Sub-Total(A3)
6379.61
637.96
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour
0.500
No.
550.00
275.00
Skilled Labour
0.250
No.
600.00
150.00
Foreman/ Supervisor
0.250
No.
850.00
212.50
Sub-Total(L1)
637.50
63.75
M2.Local Carriage,Sundr
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Local Carriage-(Labour)
0.500
No.
550.00
275.00
Sub-Total(M2)
275.00
27.50
Total(1)
729.21
Add over head on Total(1)
3.5 %
25.52
Add Profit on Total(1)
10.0 %
72.92
Total(2)
98.44
Add VAT on Unit Price
5.5 %
5.73
Unit Price
104.17
Say
104
per sqm