BREAKDOWN OF UNIT PRICE
Item:071807. Formwork (Wood) - Drop wall
Basis:63sft
D1.Prop/Pipe/I-sec/Box
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Bumboo struts-use 8 time
8.000
No.
10.62
84.96
Sub-Total(D1)
84.96
14.63
F1.Timber/ Board
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Wood for Shutter use 8-ti
6.590
cft
68.75
453.06
Sub-Total(F1)
453.06
78.03
L2.Work Rate-1
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Wood shuttering i/c makin
62.500
sft
18.00
1125.00
Sub-Total(L2)
1125.00
193.75
L3.Work Rate i/c Materi
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Making form water tight
62.500
sft
3.00
187.50
Sub-Total(L3)
187.50
32.29
M1.Miscelleneous
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Nail and wires, gazals
0.500
kg
70.00
35.00
Curing for 28 days
62.500
sft
4.58
286.25
Sub-Total(M1)
321.25
55.33
Total(1)
374.03
Add over head on Total(1)
3.5 %
13.09
Add Profit on Total(1)
10.0 %
37.40
Total(2)
50.49
Add VAT on Unit Price
5.5 %
2.94
Unit Price
53.43
Say
53
per sqm