BREAKDOWN OF UNIT PRICE
Item:071806. Formwork (Wood) - Slab
Basis:115sft
D1.Prop/Pipe/I-sec/Box
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Bamboo prop-use 8 times
25.000
No.
17.25
431.25
Sub-Total(D1)
431.25
40.37
F1.Timber/ Board
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Garjan wood use 8 times
2.180
cft
275.00
599.50
Wood for Shutter use 8-ti
7.500
cft
68.75
515.63
Sub-Total(F1)
1115.13
104.38
F2.Steel-MS/ SS
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
MS Sheet/ Plate-use 30 ti
127.500
kg
2.56
326.40
Sub-Total(F2)
326.40
30.55
L2.Work Rate-1
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Wood shuttering i/c makin
115.000
sft
18.00
2070.00
Sub-Total(L2)
2070.00
193.75
L3.Work Rate i/c Materi
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Making form water tight
115.000
sft
3.00
345.00
Sub-Total(L3)
345.00
32.29
M1.Miscelleneous
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Nail and wires, gazals
1.000
kg
70.00
70.00
Curing for 28 days
115.000
sft
4.58
526.70
Sub-Total(M1)
596.70
55.85
Total(1)
457.19
Add over head on Total(1)
3.5 %
16.00
Add Profit on Total(1)
10.0 %
45.72
Total(2)
61.72
Add VAT on Unit Price
5.5 %
3.59
Unit Price
65.31
Say
65
per sqm