BREAKDOWN OF UNIT PRICE
Item:0713. Formwork (Steel)-Arch >8m-AddRat
Basis:2434sft
D1.Prop/Pipe/I-sec/Box
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Steel Frame-Single use
608.381
sft
60.58
36855.72
Prop 9m-Single use
608.381
sft
52.84
32146.85
Sub-Total(D1)
69002.57
305.21
F2.Steel-MS/ SS
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
MS Sheet-22BWG Single use
608.381
sft
34.07
20727.54
MS Purlin-Single use
608.381
sft
8.77
5335.50
Sub-Total(F2)
26063.04
115.28
M1.Miscelleneous
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Hessain for water-tight
608.381
sft
1.50
912.57
Curing for 28 days
608.381
sft
4.58
2786.38
Sub-Total(M1)
3698.96
16.36
Total(1)
436.86
Add over head on Total(1)
3.5 %
15.29
Add Profit on Total(1)
10.0 %
43.69
Total(2)
58.98
Add VAT on Unit Price
5.5 %
3.43
Unit Price
62.41
Say
62
per sqm