BREAKDOWN OF UNIT PRICE
Item:071204. Formwork (Steel)-Column, Wall- GF
Basis:40sft
D1.Prop/Pipe/I-sec/Box
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
MS Pipe-38mm-use 50 time
32.000
rft
2.70
86.40
Turn-buckle-use 50 time
2.000
Nos.
9.00
18.00
Sub-Total(D1)
104.40
28.09
F2.Steel-MS/ SS
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
MS Angle use 30 times
80.291
kg
2.33
187.08
FI Bar-use 30 times
11.386
kg
2.33
26.53
MS Sheet/ Plate-use 30 ti
54.268
kg
2.56
138.93
Sub-Total(F2)
352.53
94.87
L2.Work Rate-1
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Fabricat Shutter-use 30t
46.670
sft
3.00
140.01
Fitting-steel shutter
40.000
sft
18.00
720.00
Sub-Total(L2)
860.01
231.43
M1.Miscelleneous
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Nut-bolt, J-hook-use 30 t
1.500
kg
5.33
8.00
Hessain for water-tight
40.000
sft
1.50
60.00
Curing for 28 days
41.000
sft
4.58
187.78
Sub-Total(M1)
255.78
68.83
Total(1)
423.22
Add over head on Total(1)
3.5 %
14.81
Add Profit on Total(1)
10.0 %
42.32
Total(2)
57.13
Add VAT on Unit Price
5.5 %
3.33
Unit Price
60.46
Say
60
per sqm