BREAKDOWN OF UNIT PRICE
Item:071201. Formwork (Steel)-Footing
Basis:41sft
F2.Steel-MS/ SS
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
MS Angle use 30 times
64.073
kg
2.33
149.29
FI Bar-use 30 times
7.636
kg
2.33
17.79
MS Sheet/ Plate-use 30 ti
47.314
kg
2.56
121.12
Sub-Total(F2)
288.21
76.35
L2.Work Rate-1
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Fabricat Shutter-use 30t
40.630
sft
3.00
121.89
Fitting-steel shutter
40.630
sft
18.00
731.34
Sub-Total(L2)
853.23
226.04
M1.Miscelleneous
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Nut-bolt, J-hook-use 30 t
1.000
kg
5.33
5.33
Hessain for water-tight
40.630
sft
1.50
60.95
Cost for support-Footing
1.000
LS
96.00
96.00
Curing for 28 days
104.630
sft
4.58
479.21
Sub-Total(M1)
641.48
169.95
Total(1)
472.34
Add over head on Total(1)
3.5 %
16.53
Add Profit on Total(1)
10.0 %
47.23
Total(2)
63.77
Add VAT on Unit Price
5.5 %
3.71
Unit Price
67.48
Say
67
per sqm