BREAKDOWN OF UNIT PRICE
Item:0710. RCC-Extra meter over 4m
Basis:100cft
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour
0.750
No.
550.00
412.50
Mason
0.200
No.
700.00
140.00
Skilled Labour
0.200
No.
600.00
120.00
Head Mason
0.100
No.
800.00
80.00
Sub-Total(L1)
752.50
265.75
M2.Local Carriage,Sundr
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Local Carriage-(Labour)
0.060
No.
550.00
33.00
Sub-Total(M2)
33.00
11.65
Total(1)
277.40
Add over head on Total(1)
3.5 %
9.71
Add Profit on Total(1)
10.0 %
27.74
Total(2)
37.45
Add VAT on Unit Price
5.5 %
2.18
Unit Price
39.63
Say
40
per cum