BREAKDOWN OF UNIT PRICE
Item:062103. Labour-Moulding Marble-12mm
Basis:38rft
E1.Equipment/ Scaffoldi
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Hire-Marble Cutting disk
1.000
day
450.00
450.00
Hire charge-Grinding m/c
2.000
day
260.00
520.00
Sub-Total(E1)
970.00
83.66
F3.Tile/ Marble
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Acid stone
1.000
No.
450.00
450.00
Water proofing paper-12sz
6.000
No.
22.00
132.00
Water proofing paper-320S
8.000
No.
24.00
192.00
Sub-Total(F3)
774.00
66.76
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Head Mason
1.500
No.
800.00
1200.00
Helper
1.500
No.
550.00
825.00
Sub-Total(L1)
2025.00
174.66
Total(1)
325.08
Add over head on Total(1)
3.5 %
11.38
Add Profit on Total(1)
10.0 %
32.51
Total(2)
43.89
Add VAT on Unit Price
5.5 %
2.55
Unit Price
46.44
Say
46
per metr