BREAKDOWN OF UNIT PRICE
Item:062102. Labour-Moulding Marble-16mm
Basis:38rft
E1.Equipment/ Scaffoldi
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Hire-Marble Cutting disk
1.000
day
450.00
450.00
Hire charge-Grinding m/c
2.000
day
260.00
520.00
Sub-Total(E1)
970.00
83.66
F3.Tile/ Marble
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Acid stone
1.000
No.
450.00
450.00
Water proofing paper-12sz
7.000
No.
22.00
154.00
Water proofing paper-320S
7.000
No.
24.00
168.00
Sub-Total(F3)
772.00
66.59
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Head Mason
2.000
No.
800.00
1600.00
Helper
2.000
No.
550.00
1100.00
Sub-Total(L1)
2700.00
232.88
Total(1)
383.13
Add over head on Total(1)
3.5 %
13.41
Add Profit on Total(1)
10.0 %
38.31
Total(2)
51.72
Add VAT on Unit Price
5.5 %
3.01
Unit Price
54.73
Say
55
per metr