BREAKDOWN OF UNIT PRICE
Item:042202. Brick Pavement-200x100x50-50mm
Basis:100sft
A1.Brick/ Blocks
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Paving Brick-200x100x50
452.000
Nos.
19.75
8927.00
Sub-Total(A1)
8927.00
960.90
A2.Cement
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Cement: CEM-II/A,52.5-PCC
2.500
bag
405.00
1012.50
Sub-Total(A2)
1012.50
108.99
A4.Earth/ Sand
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand (F.M.1.2)
13.000
cft
19.00
247.00
Sub-Total(A4)
247.00
26.59
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour
2.875
No.
550.00
1581.25
Mason
1.000
No.
700.00
700.00
Skilled Labour
2.500
No.
600.00
1500.00
Head Mason
0.250
No.
800.00
200.00
Sub-Total(L1)
3981.25
428.54
M2.Local Carriage,Sundr
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Local Carriage-(Labour)
0.500
No.
550.00
275.00
Sub-Total(M2)
275.00
29.60
Total(1)
1554.62
Add over head on Total(1)
3.5 %
54.41
Add Profit on Total(1)
10.0 %
155.46
Total(2)
209.87
Add VAT on Unit Price
5.5 %
12.21
Unit Price
222.09
Say
222
per sqm