BREAKDOWN OF UNIT PRICE
Item:041401. BrickWork-Facing 200x62x16.51-Red
Basis:100sft
A1.Brick/ Blocks
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Brick-Fac200x62x16.51-Red
704.000
Nos.
18.90
13305.60
Sub-Total(A1)
13305.60
1432.21
A2.Cement
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Cement: CEM-II/A,52.5-PCC
2.750
bag
405.00
1113.75
Sub-Total(A2)
1113.75
119.88
A4.Earth/ Sand
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand (F.M.1.2)
14.000
cft
19.00
266.00
Sub-Total(A4)
266.00
28.63
E1.Equipment/ Scaffoldi
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Scaffolding
25.000
sft
10.00
250.00
Sub-Total(E1)
250.00
26.91
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour
2.375
No.
550.00
1306.25
Mason
2.000
No.
700.00
1400.00
Skilled Labour
1.500
No.
600.00
900.00
Head Mason
1.000
No.
800.00
800.00
Sub-Total(L1)
4406.25
474.29
M2.Local Carriage,Sundr
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Local Carriage-(Labour)
1.000
No.
550.00
550.00
Sub-Total(M2)
550.00
59.20
Total(1)
2141.13
Add over head on Total(1)
3.5 %
74.94
Add Profit on Total(1)
10.0 %
214.11
Total(2)
289.05
Add VAT on Unit Price
5.5 %
16.82
Unit Price
305.88
Say
306
per sqm