Return Main Menu
BREAKDOWN OF UNIT PRICE
Item:0413. Brick Work-Facing 200x50x50-50m
Basis:100sft
A1.Brick/ Blocks
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Brick-Facing-200x50x50
856.000
Nos.
18.00
15408.00
Sub-Total(A1)
15408.00
1658.52
A2.Cement
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Cement: CEM-II/A,52.5-PCC
2.750
bag
405.00
1113.75
Sub-Total(A2)
1113.75
119.88
A4.Earth/ Sand
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand (F.M.1.2)
14.000
cft
19.00
266.00
Sub-Total(A4)
266.00
28.63
E1.Equipment/ Scaffoldi
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Scaffolding
25.000
sft
10.00
250.00
Sub-Total(E1)
250.00
26.91
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour
2.375
No.
550.00
1306.25
Mason
2.333
No.
700.00
1633.10
Skilled Labour
1.500
No.
600.00
900.00
Head Mason
1.000
No.
800.00
800.00
Sub-Total(L1)
4639.35
499.38
M2.Local Carriage,Sundr
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Local Carriage-(Labour)
0.500
No.
550.00
275.00
Sub-Total(M2)
275.00
29.60
Total(1)
2362.92
Add over head on Total(1)
3.5 %
82.70
Add Profit on Total(1)
10.0 %
236.29
Total(2)
318.99
Add VAT on Unit Price
5.5 %
18.57
Unit Price
337.56
Say
338
per sqm