BREAKDOWN OF UNIT PRICE
Item:0409. Brick Work (1:4) 3-hole m/c mad
Basis:100cft
A1.Brick/ Blocks
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Brick-3-hole m/c made
1100.000
Nos.
23.75
26125.00
Sub-Total(A1)
26125.00
9226.04
A2.Cement
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Cement: CEM-II/A,52.5-PCC
6.000
bag
405.00
2430.00
Sub-Total(A2)
2430.00
858.15
A4.Earth/ Sand
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand (F.M.1.2)
22.000
cft
19.00
418.00
Sand (F.M.2.2)
11.000
cft
53.80
591.80
Sub-Total(A4)
1009.80
356.61
E1.Equipment/ Scaffoldi
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Scaffolding
25.000
sft
10.00
250.00
Sub-Total(E1)
250.00
88.29
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour
4.375
No.
550.00
2406.25
Mason
2.000
No.
700.00
1400.00
Skilled Labour
1.500
No.
600.00
900.00
Head Mason
0.250
No.
800.00
200.00
Sub-Total(L1)
4906.25
1732.64
M2.Local Carriage,Sundr
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Local Carriage-(Labour)
0.500
No.
550.00
275.00
Sub-Total(M2)
275.00
97.12
Total(1)
12358.86
Add over head on Total(1)
3.5 %
432.56
Add Profit on Total(1)
10.0 %
1235.89
Total(2)
1668.45
Add VAT on Unit Price
5.5 %
97.11
Unit Price
1765.55
Say
1766
per cum