BREAKDOWN OF UNIT PRICE
Item:030301. Brick on End Edging
Basis:100rft
A1.Brick/ Blocks
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Brick
250.000
Nos.
10.00
2500.00
Sub-Total(A1)
2500.00
82.03
A4.Earth/ Sand
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand (FM=0.8)
2.000
cft
16.70
33.40
Sub-Total(A4)
33.40
1.10
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mason
0.200
No.
700.00
140.00
Skilled Labour
0.500
No.
600.00
300.00
Sub-Total(L1)
440.00
14.44
M2.Local Carriage,Sundr
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Local Carriage-(Labour)
0.080
No.
550.00
44.00
Sub-Total(M2)
44.00
1.44
Total(1)
99.00
Add over head on Total(1)
3.5 %
3.47
Add Profit on Total(1)
10.0 %
9.90
Total(2)
13.37
Add VAT on Unit Price
5.5 %
0.78
Unit Price
14.14
Say
14
per metr