Return Main Menu
BREAKDOWN OF UNIT PRICE
Item:030201. One Layer Herring Bone Bond (HBB)
Basis:100sft
A1.Brick/ Blocks
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Brick
500.000
Nos.
10.00
5000.00
Sub-Total(A1)
5000.00
538.20
A4.Earth/ Sand
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sand (FM=0.8)
10.000
cft
16.70
167.00
Sub-Total(A4)
167.00
17.98
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Mason
0.330
No.
700.00
231.00
Skilled Labour
1.000
No.
600.00
600.00
Sub-Total(L1)
831.00
89.45
M2.Local Carriage,Sundr
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Local Carriage-(Labour)
0.150
No.
550.00
82.50
Sub-Total(M2)
82.50
8.88
Total(1)
654.51
Add over head on Total(1)
3.5 %
22.91
Add Profit on Total(1)
10.0 %
65.45
Total(2)
88.36
Add VAT on Unit Price
5.5 %
5.14
Unit Price
93.50
Say
94
per sqm