Return Main Menu
BREAKDOWN OF UNIT PRICE
Item:021902. Bail-out water-1 cusec ElectrPump
Basis:8no.
E1.Equipment/ Scaffoldi
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Electric Pump-1 cusec
1.000
day
800.00
800.00
Elect Pump-Fuel,Maintenan
1.000
day
300.00
300.00
Sub-Total(E1)
1100.00
137.50
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Skilled Labour
2.000
No.
600.00
1200.00
Pump Operator
1.000
no.
700.00
700.00
Sub-Total(L1)
1900.00
237.50
M1.Miscelleneous
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Drainage,Connect to disch
1.000
LS
429.89
429.89
Sub-Total(M1)
429.89
53.74
M2.Local Carriage,Sundr
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sundries,Tools-plant etc
0.469
LS
550.00
257.95
Sub-Total(M2)
257.95
32.24
Total(1)
460.98
Add over head on Total(1)
3.5 %
16.13
Add Profit on Total(1)
10.0 %
46.10
Total(2)
62.23
Add VAT on Unit Price
5.5 %
3.62
Unit Price
65.85
Say
66
per hour