BREAKDOWN OF UNIT PRICE
Item:021901. Bail-out water-1 cusec DieselPump
Basis:8no.
E1.Equipment/ Scaffoldi
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Diesel Pump-1 cusec
1.000
day
1300.00
1300.00
Diesel Pump-Fuel,Maintena
1.000
day
600.00
600.00
Sub-Total(E1)
1900.00
237.50
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Skilled Labour
1.000
No.
600.00
600.00
Helper
1.000
No.
550.00
550.00
Pump Operator
1.000
no.
700.00
700.00
Sub-Total(L1)
1850.00
231.25
M1.Miscelleneous
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Drainage,Connect to disch
1.000
LS
429.89
429.89
Sub-Total(M1)
429.89
53.74
M2.Local Carriage,Sundr
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sundries,Tools-plant etc
0.469
LS
550.00
257.95
Sub-Total(M2)
257.95
32.24
Total(1)
554.73
Add over head on Total(1)
3.5 %
19.42
Add Profit on Total(1)
10.0 %
55.47
Total(2)
74.89
Add VAT on Unit Price
5.5 %
4.36
Unit Price
79.25
Say
79
per hour