BREAKDOWN OF UNIT PRICE
Item:021803. ExcavatPond-Addl lift 0.3m,3-4.5m
Basis:1000cft
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour
0.556
No.
550.00
305.80
Sub-Total(L1)
305.80
10.80
Total(1)
10.80
Add over head on Total(1)
3.5 %
0.38
Add Profit on Total(1)
10.0 %
1.08
Total(2)
1.46
Add VAT on Unit Price
5.5 %
0.08
Unit Price
1.54
Say
2
per cum