BREAKDOWN OF UNIT PRICE
Item:0217. Mechanical Compaction of Earth
Basis:7500cft
E1.Equipment/ Scaffoldi
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Hire charge-Chain Dozer
0.565
day
8200.00
4633.00
Dozer Maintenance
1.000
LS
388.44
388.44
Sub-Total(E1)
5021.44
23.64
E2.Deep Tube-well
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Diesel
108.480
litr
68.00
7376.64
Sub-Total(E2)
7376.64
34.73
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour
30.000
No.
550.00
16500.00
Skilled Labour
11.250
No.
600.00
6750.00
Sub-Total(L1)
23250.00
109.48
M2.Local Carriage,Sundr
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sundries,Tools-plant etc
5.000
LS
550.00
2750.00
Sub-Total(M2)
2750.00
12.95
Total(1)
180.80
Add over head on Total(1)
3.5 %
6.33
Add Profit on Total(1)
10.0 %
18.08
Total(2)
24.41
Add VAT on Unit Price
5.5 %
1.42
Unit Price
25.83
Say
26
per cum