BREAKDOWN OF UNIT PRICE
Item:021601. Site Develop by carted by truck
Basis:1000cft
A4.Earth/ Sand
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Royalty of earth
1150.000
cft
2.20
2530.00
Sub-Total(A4)
2530.00
89.35
E1.Equipment/ Scaffoldi
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Earth carriag-load/unload
1150.000
cft
8.50
9775.00
Sub-Total(E1)
9775.00
345.20
L1.Labour-Civil
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Ordinary Labour
8.000
No.
550.00
4400.00
Skilled Labour
1.000
No.
600.00
600.00
Sub-Total(L1)
5000.00
176.58
M2.Local Carriage,Sundr
Item
Quantity
Unit
Rate(Tk.)
Cost(Tk.)
Rate(Tk.)
Sundries,Tools-plant etc
0.409
LS
550.00
224.95
Sub-Total(M2)
224.95
7.94
Total(1)
619.07
Add over head on Total(1)
3.5 %
21.67
Add Profit on Total(1)
10.0 %
61.91
Total(2)
83.57
Add VAT on Unit Price
5.5 %
4.86
Unit Price
88.44
Say
88
per cum